West Middlesex Hospital
Chelsea and Westminster Hospital NHS Foundation Trust.
Middlesex, Healthcare, Projects
About the project
Contract type: Turnkey package
Procurement route: Unspecified
GIFA: 10 bays
Timescale: 12 weeks
The brief
The brief was to design, manufacture, and install a 10-bay Urgent Care Centre with integrated medical and support facilities.
The challenges
The build needed to take place with minimal disruption to the fully-operational A&E department.
The solution
Thurston manufactured a bespoke ten bay modular Urgent Care Unit, including groundworks, as part of a turnkey package for West Middlesex Hospital.
Designed to integrate into the existing hospital building, this brand-new facility featured fully-equipped treatment rooms and triage areas and was delivered with all necessary medical equipment. The facility also came with counselling rooms, nurses stations and a reception area, as well as a range of basic amenities including WC facilities for both staff and patients, and disabled facilities.
Using modular construction meant the project could take place offsite reducing the amount of disruption to the hospital.
Customer testimonial
West Middlesex Hospital said, “Both the staff and management are delighted with the building”.
Read our Other Recent Case Studies
Coming Soon!
Good things take time—stay tuned, new case study content is on the way!
3 min read | Matt Goff
St Cecelia’s Church of England School
The brief was to remove two temporary classrooms from an open courtyard, then design and build a two-storey, 24-bay modular classroom block.
3 min read | Matt Goff